Sydney guide

What does AS 3959 require for each BAL level in Sydney?

The higher your BAL, the tougher your materials. Here is what changes from BAL Low to BAL FZ, part by part.

Book a free consultation Call 0410 752 616
01Building designer, BDAA member
02Design, approvals and documentation
03Bushfire BAL home design

By Jay Francis, building designer and BDAA member, Francis Building Design. Updated 2 November 2026.

AS 3959 asks for tougher materials as your BAL rating climbs. At BAL Low there are no special rules.

At BAL FZ almost every part of your home is tested or protected.

I'm with Francis Building Design, a Sydney practice and BDAA member. We coordinate your bushfire assessment with council and design to these tables, so let me save you the squinting.

Francis Design concept render of a two storey home with a light brick base and a sandstone block front wall
Concept render: masonry and stone at ground level, a common starting point for higher BAL sites.

How BAL ratings shape your build

Your Bushfire Attack Level measures how hard a fire could hit your home. It covers flying embers, radiant heat and direct flame.

The levels run from lowest to highest risk:

  • BAL Low: negligible risk
  • BAL 12.5: ember attack
  • BAL 19: more embers, some heat
  • BAL 29: heavy embers, stronger heat
  • BAL 40: very high heat and embers
  • BAL FZ: direct flame contact

Not sure how you get your rating? Start with my guide to getting a bushfire assessment report.

Part by part requirements

Subfloors and floors

At BAL Low through BAL 19, there are no special subfloor or floor rules. Things change at BAL 29.

From there, you will generally need one of these:

  • A concrete slab on the ground
  • An enclosed subfloor, or metal mesh around it
  • Non combustible supports, or fire resistant timber
  • Underside protection, such as fibre cement sheet

At BAL FZ, supports and floors must meet a fire resistance level or pass bushfire testing to AS 1530.8.2.

External walls

Again, nothing special applies at the lowest levels. BAL 12.5 mostly follows BAL 19.

Lower wall sections and parts near decks need extra care. Think non combustible material, fibre cement sheeting or bushfire resisting timber.

Higher up the scale, the options shrink:

LevelTypical wall approach
BAL 29Masonry, or sarked frames with fibre cement or steel cladding
BAL 40Same idea, with thicker cladding
BAL FZThick non combustible walls, or tested systems

Windows and doors

Glass is a weak spot, so the rules get serious early. BAL 19 introduces protection such as bushfire shutters, metal mesh screens or toughened glass.

Openable sections need screening, and frames must resist fire. Metal and bushfire resisting timber are common choices.

For doors, expect these features as the rating rises:

  • Bushfire shutters or mesh screens
  • Non combustible or solid timber construction
  • Metal or fire resisting frames
  • Tight seals with weather strips at the base

At BAL FZ, shutters or fire rated doors and windows are the norm.

Roofs

Roofs are the first line of defence. From BAL 19, you will need a non combustible covering.

You will also need to:

  • Seal the roof and wall junction
  • Fit non combustible ember guards to openings
  • Sark the whole roof
Francis Design concept render of a two storey home with a simple pitched hip roof and balconies
Concept render: a simple pitched hip roof with no tight valleys for embers to settle in.

At BAL 40, roof mounted evaporative coolers are out. At BAL FZ, the roof must meet a set fire resistance level or pass testing.

Verandahs and decks

Decks feel harmless, but they can carry fire straight to your door. At lower levels, rules are light.

At BAL 29, decking near glass must be non combustible or bushfire resistant. By BAL 40 and BAL FZ, decking must be non combustible, and at FZ it needs no gaps.

From rating to finished plans

A rating is only useful once it lands in your drawings. That is why I start with Francis Building Design and your BAL on day one.

Good design weaves these rules in early. Trying to bolt them on later costs more and looks clumsy.

Here's how I like to work:

  • Confirm the BAL with your consultant
  • Choose materials that suit the rating
  • Show every requirement on the plans
  • Keep notes clear for your certifier

For the design moves that sit around these rules, see my bushfire resistant design checklist.

These requirements follow AS 3959 as summarised in industry tables. Always confirm the current standard and your consultant's report before you build.

FAQs

Common questions.

Does a higher BAL always mean a bigger budget? +

Usually, yes. Materials and detailing get tougher as the rating rises. Every site differs, so ask for pricing once your design is drawn.

Can I mix materials? +

Yes, as long as each part of the building meets your BAL. A mix often keeps costs sensible.

Where do the test standards fit in? +

AS 1530.8.1 and AS 1530.8.2 test products against bushfire exposure. A tested product can sometimes replace a listed material.

Next Step

Designing to a BAL rating?

Book a free consultation with Francis Design to turn your BAL requirements into a home you will love living in.

Free Consultation

Send a quick enquiry

Share a little about your project and Jay will come back with a tailored next step.

Call Now Book Consult